Tuesday, 17 November 2026
Newsletter Welsh Construction Today Directory

infrastructure

Jones Bros installs all 55 batteries at Ampeak's 240MWh Uskmouth storage scheme in Newport

Ampeak Energy's Afon Wysg 1 battery energy storage scheme at Uskmouth is on track to be energised in November 2026 after principal contractor Jones Bros completed installation of 55 batteries, 36 inverters and the main grid transformer.

Bar chart: Battery storage capacity of Uskmouth schemes (MWh). AW1 as built: 240; AW1 proposed expansion: 480; AW2 design capacity: 1,250.
Chart: Welsh Construction Today

Jones Bros Civil Engineering UK has installed all 55 batteries and key components for Ampeak Energy's 240MWh Afon Wysg 1 (AW1) battery storage scheme at Uskmouth in Newport, South Wales, which Ampeak said is on track to be energised this month.

The developer said AW1, its flagship battery energy storage system (BESS) project at the Uskmouth Sustainable Energy Park, is due to enter full commercial operation in the first quarter of 2027.

Jones Bros, the principal contractor, installed the batteries together with 36 inverters, 18 twin skids and the main grid transformer. The batteries were supplied and delivered by e-STORAGE, part of Canadian Solar, which will also carry out commissioning.

David Taaffe, Ampeak's CEO designate, said: "Our flagship project is a proof point in delivery. The team's success marks an important milestone for the project and brings us another step closer to delivering a significant piece of energy infrastructure for the region."

The installation

According to Jones Bros, the key components arrived over 22 days and were handled by a 10-strong delivery team, including a higher degree apprentice, which coordinated transport schedules and supplier deliveries with e-STORAGE. The equipment weighed close to 3,000 tonnes in total, Jones Bros project manager Gareth White said.

Mr White said: "It has also been fantastic to recruit locally, with our foreman and five operatives based close to Uskmouth."

The installation followed completion of the concrete foundations for the battery and power conversion system units, associated ducting and precast troughs for the inverters. Jones Bros said bulk aggregates were brought in by rail to keep HGV movements to a minimum, and concrete from earlier demolition work on the site was crushed and reused.

A new on-site substation is complete and high-voltage cabling for the grid connection has been installed. About two thirds of the former power station's export cable was reused, which the contractor said cut both time and cost. An attenuation pond, new fencing and landscaping have been delivered under the project's ecological enhancement plan.

Expansion to 480MWh

Ampeak said development work to double AW1's capacity to 480MWh is well progressed, with the aim of reaching financial close on the expansion shortly after the current milestone. Space has been left between the batteries and foundations for the additional units have already been poured so the expansion can be built quickly.

Matt Paterson, managing director, EMEA, at e-STORAGE, said in the announcement that the poured foundations mean AW1 can grow without repeating the groundwork.

Directors of Jones Bros also hold a stake in the scheme. Ampeak has said that JB Energy, a special purpose vehicle owned by directors of Jones Bros. Ruthin (Civil Engineering) Co. Limited, acquired a 24.7% equity stake in AW1 Storage Holdings Ltd. Ampeak Energy remains the majority owner of the holding company.

Background

Jones Bros's AW1 contract is a £19m civils and electrical package, according to its contract-award announcement. The scope included levelling the site and building up a raised main platform to reduce flood risk. At award, the contractor said Mr White would lead a team of up to 30 on site, including three trainees and one higher degree apprentice.

Ampeak, which was previously known as SAE, has said that it discharged all pre-commencement planning conditions for the 120MW/240MWh project, the first battery storage scheme it will build, own and operate itself. The company has also said the 120MW project secured a 15-year Capacity Market contract in the T-4 auction at £60/kW/year, and that it secured an £8.5m loan from Cardiff Capital Region's Strategic Premises Fund for the scheme.

Ampeak says the Uskmouth site, which has hosted electricity generation for more than 50 years, can support about 3.5GWh of battery storage. A second project, AW2, is designed for a total capacity of 1,250MWh.

Scheme Capacity (MWh)
AW1 as built 240
AW1 proposed expansion 480
AW2 design capacity 1,250

Jones Bros was established in the 1950s and employs about 570 people. The company says its apprenticeship scheme has produced nearly 40% of its current workforce.

Ampeak said the next milestone will be the first energisation of the batteries from the grid later in November 2026, followed by charge and discharge commissioning ahead of commercial operation in Q1 2027.

Sources

  1. Jones Bros Civil Engineering UK (opens in a new tab) (accessed 2026-11-13)
  2. Ampeak Energy (opens in a new tab) (accessed 2026-11-13)
  3. Ampeak Energy (opens in a new tab) (accessed 2026-11-13)
  4. Ampeak Energy (then SAE) (opens in a new tab) (accessed 2026-11-13)
  5. Ampeak Energy (then SAE) (opens in a new tab) (accessed 2026-11-13)
  6. Ampeak Energy (then SAE) (opens in a new tab) (accessed 2026-11-13)
  7. Ampeak Energy (opens in a new tab) (accessed 2026-11-13)
  8. Jones Bros Civil Engineering UK (opens in a new tab) (accessed 2026-11-13)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Welsh Construction Today weekly: the week's construction news from wales in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Welsh Construction Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Welsh Construction Today