TfW plans replacement bus operation for £25m North Wales Coast closure in January 2027
Transport for Wales has set out how it will move passengers while Network Rail closes the Chester to Holyhead line for track renewals at Conwy, Bodorgan, Penmaenbach, Holyhead and Llandudno.

Transport for Wales (TfW) has published plans for one of its biggest ever rail replacement operations to cover a £25m Network Rail engineering programme that will close the North Wales Coast line in January and February 2027.
TfW said on 12 November that no trains will run between Chester and Holyhead, or on the Conwy Valley line, from Saturday 9 to Friday 29 January 2027. From Saturday 30 January, trains return between Chester and Llandudno Junction and on the Conwy Valley line, while TfW said the section between Llandudno Junction and Holyhead stays closed until Friday 5 February. Network Rail's project page and a Welsh Government written statement give the closure as 9 January to 6 February 2027.
The programme includes track renewals and upgrades at the Conwy Tubular Railway Bridge, Bodorgan Tunnel, Penmaenbach, Holyhead and Llandudno, with some infrastructure receiving significant investment for the first time since the 1970s, according to TfW. It also covers platform improvements at Llandudno Junction and two new active travel footbridges, which TfW named as Prestatyn and Pensarn.
Emma Osborn, Passenger Strategy Director at Network Rail, said: "this £25 million programme will see our teams deliver several years' worth of essential upgrades in just four weeks."
The replacement service
TfW said limited-stop buses will run every 30 minutes between Chester and Holyhead, calling only at Colwyn Bay, Llandudno Junction and Bangor. These will operate alongside all-stations buses every 30 minutes between Chester and Bangor and hourly between Bangor and Holyhead.
Colin Lea, Planning & Performance Director at TfW, said: "Bringing rail replacement management in-house has allowed us to better coordinate our bus and rail operations."
Avanti West Coast will run its hourly London Euston to Chester service during the first three weeks of the closure, with its trains running to and from Llandudno Junction in the final week, TfW said.
Separate engineering work at Chester station will close platforms 1 to 4 on three January weekends. TfW said Wrexham General to Chester trains will be replaced by buses on Sunday 10 January, Saturday 16 and Sunday 17 January, and Saturday 23 and Sunday 24 January. Manchester to Cardiff services run as normal throughout.
Why a single closure
TfW said the work was scheduled for January to reduce the impact on tourism and local businesses, and that closing the railway for four weeks allows several years' worth of complex work to be completed in one go. Network Rail's project page says one continuous closure "reduces overall disruption and lowers project costs" compared with repeated weekend or overnight closures.
Network Rail announced the planned closure on 16 June 2026 as part of the Network North Wales investment. Network Rail describes the programme as costing more than £25m, while TfW gives the figure as £25m.
Devolution question
The closure has also been the subject of a Welsh Government written statement. In the statement, dated 22 October 2026, Mark Hooper MS, Deputy Minister for Transport, linked the decision to the case for rail devolution, saying that "Welsh Ministers should be part of the decision making on matters as significant as closing a railway line in Wales".
TfW said replacement journeys will appear on its app, website and journey planners, and that bus coordinators will be based at key interchange stations during the closure. Passengers needing assistance are asked to book Passenger Assist in advance, with all replacement coaches described as fully accessible.
The first day of the closure is Saturday 9 January 2027.
Sources
- Transport for Wales (opens in a new tab) (accessed 2026-11-13)
- Transport for Wales (opens in a new tab) (accessed 2026-11-13)
- Network Rail (opens in a new tab) (accessed 2026-11-13)
- Network Rail (opens in a new tab) (accessed 2026-11-13)
- Welsh Government (opens in a new tab) (accessed 2026-11-13)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.